Weekly Status 2016-04-25
Post date: May 4, 2016 5:45:35 PM
Not much happened over the previous few weeks, so no statuses.
Jeff Trayhan / Patriot Mechanical has four proposals pending with Everest; Peter will cost them and deliver proposals to the HOA early this week:
1) Trash Room
- supply/install new ceiling fan in trash room, with electrical et al
- install 8” round duct in front stairwell, route through holes in landings, to exit roof near the stairwell roof hatch
- install 12” damper, with grills, at roofline
- Peter will quote work to cut holes in landings, roof, and drywall at trash room, add quote from Jeff, balance against pre-quoted work for trash room
- elevator sump work was not discussed, but is assumed to be part of this effort
2) Replacement of Galvanized Roof Sections
- new work based on discovery during other weatherproofing operations
- remove/replace north and south roof sections
- install trash room damper during this process
- all Patriot work, no Everest involvement
3) Intake/Exhaust Fans
- install VFD, pressure sensor et al in ventilation fan
- relocate exhaust fan with new enclosure to existing concrete pad
4) Hallway Fire Dampers
- no definite direction from Bruce, nor complete list of dampers to replace
- some quantity of indecision re repair vs replace vs reconfigure with additional alarm wiring
- some dampers difficult to get to- need to Sawzall existing damper out, remove ducting, install new one
- with no advice to the contrary, Lee requested that all dampers be replaced with identical new (non-defective) units, using the same activation strategy as the existing system
- per the 3/31 status, replacement dampers should have arrived first week of April …?
5) Namgyal Ongoing
- PortaPotty removed from site two weeks ago
- additional repair work in 203, and windows in 101, is pending delivery of silicone tape, Nam return from trip
- per John Dunlap- a window issue on the 201 Rausch side needs investigation
- this probably includes a window leak remediation strategy and window water testing; undiscussed
- no news re a cover for the boiler room floor drain
- no news re touch-up painting of the 4th-floor deck
6) 105 Street Entry Grating
- John Paul supplied sample part numbers for a floor grate that would work
- Lee will forward to Derek and Peter