Weekly Status 2015-10-19
Post date: Oct 19, 2015 5:26:10 PM
0) Completions
- 4th-floor common and private decks are done and ready for the color coat
1) Decks
- work is near-complete on the 4th-floor decks- surface prep and all layers except color
- per Anna and Nam, Westcoat reps have been following the process and are agreeing with the surface prep and application process
- Nam will do three color samples today for review by the HOA:
2) Wall Coating
- the pull tapes for adhesion testing seemed to come off a little too easily
- Anna recommends redoing the tests on a surface prepped identically to the rest of the building; i.e., pressure-washed
- Nam will redo the test areas (takes a week for curing), then invite a rep from Dow Corning to observe the tests for warranty purposes
- wall coatings are around 10 days behind schedule. Peter will do schedule updates.
3) Interior Mechanical
- all units reviewed except 102 and 104- try to pick them up this week
- Peter is creating a list of per-unit changes
4) 4th-floor Doors
- doors are ordered, delivery <= 4 weeks
5) IGU Replacements
- CO is pending with the HOA, waiting on identification of further fogged units in unit 201
6) 304 Ventilation
- unit 304 has (had?) disabled ventilation air, resulting from a closed fire damper in the hallway
- repair is pending later addressing of the larger fire damper issues