Weekly Status 2016-03-14
Post date: Mar 14, 2016 11:55:33 PM
1) Mechanical Phase 2
- Bruce is working through equipment selection and specifications, delivering docs to Jeff at Patriot on Friday
- Jeff is responding with questions and working out implementation details
2) Entryway Glass
- Awning glass is ready
- waiting on 24h of dry weather for installation
3) 105, 301, 402
- 105 - waiting on grate spec from Anna and Derek
- 301 windows, touch-up painting- Thur/Fri
- 402 windows, touch-up painting- Thur/Fri
4) 4th-Floor Deck
- Deck has been cleaned
- Nam will do touch-up painting next week
- 401 can move all items back onto the deck at that time, clearing the exterior stairway landing
5) Boiler Room
- Hetherington Plumbing did overflow piping on Friday; unclear re status
- Nam will fab and install a cover for the defective floor drain when plumbing work complete
6) Water Tests
- Nam and Anna have a tentative date this week to initiate water tests on 101, 201, 301 windows
- Target Thur/Fri for tests