Weekly Status 2016-01-25
Post date: Jan 28, 2016 7:29:44 PM
1) 401 Door Replacement
- Door contractor is done, but residents have a punch list
- Lee also noted that the post between the 402 doors is missing exterior cladding
- Anna will set up a date with Nam to schedule water testing, probably next week
2) 105 Threshold and Landing Leaks
- John Paul still has water coming through the foundation wall, both from the top and through in-wall cracks
- Derek wants to examine the sheet goods on the exterior to understand the conditions
- Everest will do some localized excavating around the door, as well as removing the threshold for better sealing
3) Window Bulb Seals
- Incorrect seal stock has been returned
- A sample of the correct seal has been sent; the warehouse will deliver it in 4-5 working days
4) Entryway Roof Glass
- Should have a sample for approval, but Nam wasn’t on the call so no news
5) Mechanical
- 304 is done. Lee inspected, believes it looks good. Anna wants to see it, too.
- 301 being worked on
- 303- can’t find owners, so no access at the moment
- Peter heard from both Bruce and Meng. Meng is trying to figure out what to do re a proposal.
- Goal- nail down a mechanical engineer by next Monday
6) 301 Hallway Roof Leak
- Late-breaking news- leak caused by leaking overflow in boiler room
- Everest applied temp fix; Heatherington to provide permanent fix
7) Figley and East Wall Paint Certification
- Still waiting