Weekly Status 2016-01-25

Post date: Jan 28, 2016 7:29:44 PM

1) 401 Door Replacement

  • Door contractor is done, but residents have a punch list
  • Lee also noted that the post between the 402 doors is missing exterior cladding
  • Anna will set up a date with Nam to schedule water testing, probably next week

2) 105 Threshold and Landing Leaks

  • John Paul still has water coming through the foundation wall, both from the top and through in-wall cracks
  • Derek wants to examine the sheet goods on the exterior to understand the conditions
  • Everest will do some localized excavating around the door, as well as removing the threshold for better sealing

3) Window Bulb Seals

  • Incorrect seal stock has been returned
  • A sample of the correct seal has been sent; the warehouse will deliver it in 4-5 working days

4) Entryway Roof Glass

  • Should have a sample for approval, but Nam wasn’t on the call so no news

5) Mechanical

  • 304 is done. Lee inspected, believes it looks good. Anna wants to see it, too.
  • 301 being worked on
  • 303- can’t find owners, so no access at the moment
  • Peter heard from both Bruce and Meng. Meng is trying to figure out what to do re a proposal.
  • Goal- nail down a mechanical engineer by next Monday

6) 301 Hallway Roof Leak

  • Late-breaking news- leak caused by leaking overflow in boiler room
  • Everest applied temp fix; Heatherington to provide permanent fix

7) Figley and East Wall Paint Certification

  • Still waiting