Weekly Status 2015-06-01

Post date: Jun 1, 2015 4:12:48 PM

1) Contractor bid walk of the building is tomorrow (Tuesday) 6/2, 1:00p. We have access to units 105 and 204; I’m looking for 3rd-floor deck access through one of those units. Derek has asked that I point out wall penetrations that might be causing sound / odor issues.

2) Bid deliveries are scheduled for next Tuesday. The bid review meeting will be a few days later, probably Thursday or Friday.