Weekly Status 2016-03-07

Post date: Mar 7, 2016 6:07:29 PM

This status covers the previous two weeks; Lee, Nam, and Anna on the phone.

1) Mechanical Phase 1

  • 303 dryer ducting work was completed last Thursday
  • All 3rd-floor dryer duct work is complete; Anna will inspect one of the installations in the next few days
  • 104 booster fan initiation may still be an issue, waiting on Bruce Allen for something
  • Remaining sound boxes have been installed

2) Mechanical Phase 2

  • Bruce Allen (Lefler Engineering), Jeff Trayhan (Patriot), Nam, and Lee did a mechanical walk-around on Thur 2/25, reviewing all the phase 2 work in detail
  • Review covered trash room venting, removal of the existing trash room vent duct in unit 105, ventilation fire damper actuator replacements, relocation of the exhaust fan to the concrete pad on the boiler room roof, installation of a VFD in the fresh air system, design and fab of new leaf guards for the air intake
  • Bruce promised that he would start on spec work the following day with a goal to beginning work the following week, but no apparent action to date
  • Peter Vorhees and Lee are both following up with Bruce

3) Entryway Awning Glass

  • Garmison Glass was unavailable last week, should be around this week to install the new glass over the entryway
  • Nam has two samples of plastic covers, will leave by John’s unit for review and approval by John and/or Lee

4) Ground Floor Doors

  • All eyebrow installations and glass wet-seals over the first-floor exterior doors are complete

5) Unit 105 threshold

  • John Paul has requested a permeable solution for the pavement outside his door (metal grate over gravel)
  • Derek/MCA will spec something; Anna is following up with him

6) Unit 301 Items

  • Nam has replacement wire glass to install and window frame reinforcements, and paint touchups on the ceiling repair
  • Waiting on a response from Seth for scheduling

7) Unit 402 Items

  • Jason is back from traveling
  • Nam will contact him to schedule installation of 3 IGUs, detail touchups re his patio doors

8) Water Testing

  • Anna wants to complete the contracted water tests
  • Lee suggested choosing an east elevation wire glass window with the new wet seals, and other windows where Everest can prototype seal options for future repairs
  • Anna and Nam will schedule a test day next week around windows in units 101, 201, and 301
  • Lee will ask residents about leaks from the latest storms