1) Mechanical Phase 2
- Mechanical work is stalled (trash room, metal roof replacement, intake/exhaust fans, fire damper actuators)
- Peter at Everest has had higher priority tasks over the last six weeks and has been unable to integrate quotes from Patriot Mechanical
- Lee has asked McGinnis Chen for help and ideas re moving things forward
2) Namgyal Ongoing
- Nam was traveling, is back and reviewing issues
- additional repair work in 203, and windows in 101, is pending delivery of silicone tape
- per John Dunlap- a window issue on the 201 Rausch side needs investigation
- this probably includes a window leak remediation strategy and window water testing; undiscussed
- no news re a cover for the boiler room floor drain
- no news re touch-up painting of the 4th-floor deck
3) Unresolved Water Intrusion Issues
- 203: window leaks cause window sill puddling
- 204: slow drip from lighting hanger
- 402: leak through vent penetration
- some of these may be complete, just don’t have closure
4) 105 Street Entry Grating
- Lee forwarded JPs suggested solution to Derek and Peter
5) Exterior Lighting Update
- Lee has a check for Universal Electric for lighting fixtures, will execute order this week
- lead times 4-6 weeks
- not a reconstruction issue, but worth tracking here