Weekly Status 2015-07-27

Post date: Aug 4, 2015 7:24:02 PM

1) Anna and Derek at MCA are working with Peter Vorhees at Everest re completing the contract. Anna discovered a possible discrepancy in the Everest bid where a spall repair task was counted twice; she’s talking to Peter today to resolve the issue and complete the contract language. If she’s correct, there will be a net decrease in the overall bid cost.

2) MCA is targeting a Wednesday delivery of a draft contract to Ann Rankin for legal review. Lee will connect with Ann and verify that she’s ready to review it.

3) MCA doesn’t need anything from the HOA this week. Lee will begin notifying unit owners that work is coming up.