Deck resurfacing is completely done, with all plants and furniture replaced
The Rausch elevation (courtyard side) has a complete first wall coating
1) Remediation
Debris removal in unit 204 will be complete on Monday
Hygienist review on Tuesday; area should be cleared for reconstruction by Wed morning
Lee with check with PMC re the status of the disposal form (complete late Monday)
Drywall installation starts Friday, runs through mid-next week. Reconstruct as originally built- 2-layer 1/2” drywall over fiberglass insulation, painted white.
Do this process in 105 after 12/5. Investigate the under-stairs area with the drywall out to inspect for potential water intrusion issues.
Do this process in 401 a few days before the new French doors arrive.
2) Rausch elevation (courtyard side)
Caulking done, rusted sills cleaned up and primed
Base coat complete over entire wall
Removed all existing paint- only one original coat, versus Sumner/Clementina with multiple coats (and multiple paint types) over graffiti et al
Anna: should do pull test, given different conditions. Nam agreed, will do.
Derek and Anna reviewed spalled northeast corner and repair procedure, suggested leaving the existing flashing and creating a sealed joint with the patched joint.
Anna noted that the new metal is close to the surface, and that the surface might need to be a little higher than a perfect plane. Nam verified that there’s at least 1/2” of concrete over the rebar.
3) Mechanical
205 is done, 101 done Monday morning; 103 or 104 next depending on access
304 has ventilation as of last Friday, with a fix to a stuck damper. Unclear how the damper was fixed, and whether there’s information there re other stuck dampers. Peter will talk to Patriot to get more information.
Patriot has a list of work per unit, but hasn’t shared it. Peter and Nam will work to get updates and produce a final work list.
4) IGU replacements
New window panes should be delivered on Monday this week
Install 101, 201 replacements first, on Rausch side, then move around to Sumner/Clementina
5) Exterior lighting
Lee is talking to a lighting vendor (RAB) to get a fixture spec
Lee is also investigating a couple other lighting changes- replace the lighting on the 4th-floor common deck, and add a light over the main entrance
6) Security
People are climbing the scaffolding trying to get in. One person stepped on the glass over the entrance and broke one of the panels.
Nam is investigating adding barb wire to the staging to discourage climbing
There’s also an issue with people getting into the lobby and setting up camp in the trash room. Sub-contractors need to keep the front door closed.